Published on: June 7, 2024

NAMMA METRO’S PINK LINE TUNNELLING

NAMMA METRO’S PINK LINE TUNNELLING

NEWS – Namma Metro’s Pink Line Tunnelling Deadline at Risk Due to Rocky Terrain Challenges

HIGHLIGHTS

Overview

  • Project at Risk: The underground tunneling for Bengaluru Metro’s Pink Line faces delays.
  • Challenges: Rocky terrain encountered by Tunnel Boring Machines (TBMs) may extend the project timeline beyond the August 2024 deadline.

TBMs Deployment and Progress

  • Nine TBMs Deployed: BMRCL utilized nine Tunnel Boring Machines for the project.
    • Successful Completions: Seven TBMs (Urja, Varada, Avni, Lavi, Vindhya, Vamika, and Rudra) have finished their tasks.
    • Ongoing Work: TBMs Tunga and Bhadra are still operational.

Specifics of Tunga and Bhadra

  • Tunga’s Task: Final push from K.G. Halli to Nagavara, covering 935 meters.
  • Bhadra’s Task: Digging a 939-meter tunnel northbound from K.G. Halli to Nagavara.
  • Challenges Encountered: Both TBMs are facing rocky terrain which is slowing progress.
    • Expected Progress: Normally 5 kilometers per day.
    • Current Progress: Reduced to 3 kilometers per day due to rock formations.

Impact on Timeline

  • Potential Delays: The rocky terrain could result in missing the original deadline.
    • Anticipated Delay: A few days beyond the initial August 2024 deadline.

Lengthiest Underground Section of Pink Line

  • Project Scope: Pink Line spans 21.26 km from Kalena Agrahara to Nagavara.
    • Underground Segment: 13.76 km, making it the longest underground section of the Bengaluru metro.
    • Twin Tunnels: 20.992 km of twin tunnels under construction.
    • Stations: 18 stations, including 12 underground and six elevated stations, nearing completion.

Historical Delays

  • Previous Challenges:
    • Tender Cancellation: Due to high bids.
    • Alignment Changes: Required before final approval.
    • Land Acquisition: Issues led to delays.
  • Current Expectations: Entire stretch may open in 2025 due to cumulative delays.